Tap any paragraph to write a margin note. Your notes collect in the Desk below the text and file under cases with @. The side-by-side margin rail opens on a larger screen.

Code · CFR · Title 24 — Housing and Urban Development · Part 35 — Lead-Based Paint Poisoning Prevention in Certain Residential Structures · § 35.830

§ 35.830. Child with an elevated blood lead level.

1,266 words·~6 min read·/us/cfr/t24/s§ 35.830·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)Environmental investigation. Within 15 calendar days after being notified by a public health department or other medical health care provider that a child of less than 6 years of age living in a dwelling unit owned by HUD (or where HUD is mortgagee-in-possession) has been identified as having an elevated blood lead level, HUD shall complete an environmental investigation of the dwelling unit in which the child lived at the time the blood was last sampled and of common areas servicing the dwelling unit. The requirements of this paragraph apply regardless of whether the child is or is not still living in the unit when HUD receives the notification of the elevated blood lead level. The requirements of this paragraph shall not apply if HUD conducted an environmental investigation of the unit and common areas servicing the unit between the date the child's blood was last sampled and the date when HUD received the notification of the elevated blood lead level. If HUD conducted a risk assessment of the unit and common areas servicing the unit during that period, HUD is not required to conduct another risk assessment there but it shall conduct the elements of an environmental investigation not already conducted during the risk assessment. If a public health department has already conducted an evaluation of the dwelling unit in regard to the child's elevated blood lead level case, the requirements of this paragraph shall not apply.
(b)Verification. After receiving information from a person who is not a medical health care provider that a child of less than 6 years of age living in a dwelling unit covered by this subpart may have an elevated blood lead level, HUD shall immediately verify the information with the public health department or other medical health care provider. If the public health department or provider denies the request, such as because it does not have the capacity to verify that information, the HUD Realty Specialist assigned to that property shall send documentation of the denial to the HUD Office of Lead Hazard Control and Healthy Homes, which shall make an effort to verify the information. If the public health department or provider verifies that the child has an elevated blood lead level, such verification shall constitute notification, and HUD shall take the action required in paragraphs
(a)and
(c)of this section.
(c)Lead-based paint hazard reduction. Within 30 calendar days after receiving the report of the environmental investigation conducted pursuant to paragraph
(a)of this section or the evaluation from the public health department, HUD shall complete the reduction of identified lead-based paint hazards in accordance with § 35.1325 or § 35.1330. Lead-based paint hazard reduction is considered complete when clearance is achieved in accordance with § 35.1340 and the clearance report states that all lead-based paint hazards identified in the environmental investigation have been treated with interim controls or abatement or the public health department certifies that the lead-based paint hazard reduction is complete. The requirements of this paragraph do not apply if HUD, between the date the child's blood was last sampled and the date HUD received the notification of the elevated blood lead level, already conducted an environmental investigation of the unit and common areas servicing the unit and completed reduction of identified lead-based paint hazards. If HUD conducted a risk assessment of the unit and common areas servicing the unit during that period, it is not required to conduct another risk assessment there but it shall conduct the elements of an environmental investigation not already conducted during the risk assessment.
(d)Notice. If lead-based paint hazard evaluation or reduction is undertaken, each owner shall provide a notice to occupants in accordance with § 35.125.
(e)Reporting requirement.
(1)HUD shall report the name and address of a child identified as having an elevated blood lead level to the public health department within 5 business days of being so notified by any other medical health care professional.
(2)HUD shall also report each confirmed case of a child with an elevated blood lead level to the HUD Office of Lead Hazard Control and Healthy Homes within 5 business days of being so notified.
(3)HUD shall provide to the HUD Office of Lead Hazard Control and Healthy Homes documentation that it has conducted the activities of paragraphs
(a)through
(d)of this section, within 10 business days of the deadline for each activity.
(f)Other assisted dwelling units in the property.
(1)If the environmental investigation conducted pursuant to paragraph
(a)of this section identifies lead-based paint hazards, HUD shall, for other assisted dwelling units covered by this part in which a child under age 6 resides or is expected to reside on the date lead-based paint hazard reduction under paragraph
(c)of this section, and the common areas servicing those units, is complete, conduct a risk assessment in accordance with § 35.815 within 30 calendar days after receipt of the environmental investigation report if there are 20 or fewer such other units, or 60 calendar days if there are more than 20 such other units.
(2)If the risk assessment conducted under paragraph (f)(1) of this section identifies lead-based paint hazards, HUD shall complete the reduction of identified lead-based paint hazards in accordance with § 35.1325 or § 35.1330 in those units and common areas within 30 calendar days, or within 90 calendar days if more than 20 units have lead-based paint hazards such that the control work would disturb painted surfaces that total more than the de minimis threshold of § 35.1350(d). Lead-based paint hazard reduction is considered complete when clearance is achieved in accordance with § 35.1340 and the clearance report states that all lead-based paint hazards identified in the risk assessment have been treated with interim controls or abatement.
(3)The requirements of this paragraph
(f)do not apply if:
(i)HUD, between the date the child's blood was last sampled and the date HUD received the notification of the elevated blood lead level, both conducted a risk assessment in the other assisted dwelling units covered by paragraph (f)(1) of this section and the common areas servicing those units, and conducted interim controls of identified lead-based paint hazards in accordance with § 35.820; or
(ii)HUD has documentation of compliance with evaluation, notification, lead disclosure, ongoing lead-based paint maintenance, and lead-based paint management requirements under this part throughout the 12 months preceding the date HUD received the environmental investigation report pursuant to paragraph
(a)of this section.
(4)HUD shall provide to the HUD Office of Lead Hazard Control and Healthy Homes documentation that it has conducted the activities of paragraph (f)(1) through
(2)of this section, or that it has complied with the requirements in paragraph (f)(3) of this section, within 10 business days of the deadline for each activity.
(g)Closing. If the closing of a sale is scheduled during the period when HUD is responding to a case of a child with an elevated blood lead level, HUD may arrange for the completion of the procedures required by paragraphs
(a)through
(d)of this section by the purchaser within a reasonable period of time.
(h)Extensions. The Assistant Secretary for Housing-Federal Housing Commissioner or designee may consider and approve a request for an extension of deadlines established by this section for lead-based paint inspection, risk assessment, environmental investigation, lead-based paint hazard reduction, clearance, and reporting. Such a request may be considered, however, only during the first six months during which HUD is owner or mortgagee-in-possession of a multifamily property. \[82 FR 4168, Jan. 13, 2017\]
Connections2 cite this
Citation graph
cites case law
§ 35.830
Child with an elevated blood lead level.
Fed. Reg.×2
Cites 0Cited by 2 across 1 source
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.